|
1. Preamble
Promotion of competition in the electricity industry in India
is one of the key objectives of the Electricity Act, 2003 (the Act).
Power purchase costs constitute the largest cost element for distribution
licensees. Competitive procurement of electricity by the distribution
licensees is expected to reduce the overall cost of procurement
of power and facilitate development of power markets. Internationally,
competition in wholesale electricity markets has led to reduction
in prices of electricity and in significant benefits for consumers.
Section 61 & 62 of the Act provide for tariff regulation and
determination of tariff of generation, transmission, wheeling and
retail sale of electricity by the Appropriate Commission. Section
63 of the Act states that –
“Notwithstanding anything contained in section 62, the
Appropriate Commission shall adopt the tariff if such tariff has
been determined through transparent process of bidding in accordance
with the guidelines issued by the Central Government.”
These guidelines have been framed under the above provisions of
section 63 of the Act. The specific objectives of these guidelines
are as follows:
- Promote competitive procurement of electricity by distribution
licensees;
- Facilitate transparency and fairness in procurement processes;
- Facilitate reduction of information asymmetries for various
bidders;
- Protect consumer interests by facilitating competitive conditions
in procurement of electricity;
- Enhance standardization and reduce ambiguity and hence time
for materialization of projects;
- Provide flexibility to suppliers on internal operations while
ensuring certainty on availability of power and tariffs for buyers.
2. Scope of the Guidelines
2.1. These guidelines are being issued under the provisions of
Section 63 of the Electricity Act, 2003 for procurement of electricity
by distribution licensees (Procurer) for:
- long-term procurement of electricity for a period of 7 years
and above;
- Medium term procurement for a period of upto 7 years but exceeding
1 year.
2.2. The guidelines shall apply for procurement of base-load, peak-load
and seasonal power requirements through competitive bidding, through
the following mechanisms:
(i) Where the location, technology, or fuel is not specified by
the procurer (Case 1);
(ii) For hydro-power projects, load center projects or other location
specific projects with specific fuel allocation such as captive
mines available, which the procurer intends to set up under tariff
based bidding process (Case 2).
2.3. Unless explicitly specified in these guidelines, the provisions
of these guidelines shall be binding on the procurer. The process
to be adopted in event of any deviation proposed from these guidelines
is specified later in these guidelines under para 5.16.
2.4. Procurement by more than one distribution licensee through
a combined bid process shall be permitted. For such combined procurement,
each procurer shall provide the necessary information required as
per these guidelines. To ensure standardization in evaluation of
bids, the payment security and other commercial terms offered to
the bidders by the various procurers shall not vary. The price offered
by the bidders shall also be the same for the distribution licensees
inviting the bid.
2.5. All obligations on part of the procurers for the bid process
shall be considered to be met only when each and every procurer
meets such obligations set out in the Request for Proposal (RFP).
This shall, however, not preclude the bidder from waiving such stipulation
if the bidder finds it reasonable to do so, and the same shall not
be construed to be violation of these guidelines.
3. Preparation for inviting bids
3.1. To expedite the bid process, the following conditions shall
be met by the procurer:
- The bid documentation shall be prepared in accordance with
these guidelines and the approval of the appropriate Regulatory
Commission shall be obtained unless the bid documents are as per
the standard bid documents issued by the Central Government. In
such cases, an intimation shall be sent by the procurer to the
appropriate Regulatory Commission about initiation of the bidding
process.
- Approval of the Appropriate Commission shall be sought in event
of the deviations from the bidding conditions contained in these
guidelines, following the process described in para 5.16 of these
guidelines.
- Approval of the Appropriate Commission shall be sought prior
to initiating the bidding process in respect of the following
aspects:
(a) For the quantum of capacity / energy to be procured, in case
the same is exceeding the projected additional demand forecast
for next three years (Both for Case 1 and Case
2).
(b) For the transfer price of fuel, in case of fuel specific procurement
enquiry, if such price has not been determined by government,
government approved mechanism or a fuel regulator (under Case
2).
3.2. For long-term procurement from hydro electric projects or
for projects for which pre-identified sites are to be utilized (Case
2), the following activities should be completed by the procurer,
or authorized representative of the procurer, before commencing
the bid process:
- Site identification and land acquisition required for the project
- Environmental clearance
- Fuel linkage, if required (may also be asked from bidder)
- Water linkage
- Requisite Hydrological, geological, meteorological and seismological
data necessary for preparation of Detailed Project Report (DPR),
where applicable.
The bidder shall be free to verify geological data through his
own sources, as the geological risk would lie with the project developer.
The project site shall be transferred to the successful bidder
at a declared price.
3.3. It is recommended that the procurer should obtain the transmission
clearances necessary for receiving power at the delivery points
prior to inviting bids. However this shall not be a binding condition
for the bid process. Unless otherwise specified in the bid documents,
it shall be the responsibility of the selected bidder to obtain
transmission linkage for evacuation and inter-State transmission
of power (where applicable).
4. Tariff Structure
4.1. For procurement of electricity under these guidelines, tariff
shall be paid and settled for each payment period (not exceeding
one month). A multi-part tariff structure featuring separate capacity
and energy components of tariff shall ordinarily form the basis
for bidding. However, for medium term procurement the procurer may,
at his option, permit bids on a single part basis, and the same
shall be clearly specified in the Request for Qualification (RFQ)
/ Request for Proposal (RFP).
4.2. In case of long term procurement with specific fuel allocation
(Case 2), the procurer shall invite bids on the basis of capacity
charge and net quoted heat rate. The net heat rate shall be ex-bus
taking into account internal power consumption of the power station.
The energy charges shall be payable as per the following formula
:
Energy Charges = Net quoted heat rate X Scheduled Generation
X Monthly Weighted Average Price of Fuel / Monthly Average Gross
Calorific Value of Fuel.
If the price of the fuel has not been determined by the Government
of India, government approved mechanism or the Fuel Regulator, the
same shall have to be approved by the appropriate Regulatory Commission.
In case of coal / lignite fuel, the cost of secondary fuel oil
shall be factored in the capacity charges.
4.3. Tariffs shall be designated in Indian Rupees only. Foreign
exchange risks, if any, shall be borne by the supplier. Transmission
charges in all cases shall be borne by the procurer.
Capacity charges
4.4. Capacity charge shall be paid based on actual availability
in kwh, as per charges quoted in Rs/kwh and shall be limited to
the normative availability (or normative capacity index for hydro
electric stations). The normative availability shall be aligned
to the level specified in the tariff regulations of the Central
Electricity Regulatory Commission (CERC) prevailing at the time
of the bid process, and shall be computed on annual basis. The capacity
component of tariffs may feature separate non-escalable (fixed)
and escalable (indexed) components. The indices to be adopted for
escalation of the escalable component shall only be Wholesale Price
Index (WPI) or Consumer Price Index (CPI) and the Base year shall
be specified in the bid document.
4.5. Capacity charges for supply beyond the normative availability
shall be a pre-specified percentage of the non-escalable component
of the capacity charges, and shall be based on the availability
of the plant beyond the normative availability. The percentage applicable
shall be specified in the RFP, and shall be limited to a 40% of
the non-escalable component of the capacity charges. For procurement
of Case-2 type (in reference to para 2.2.), the procurer shall have
first right of refusal on energy generated beyond normative availability.
In case actual availability is less than the normative availability,
capacity charges shall not be payable for the shortfall compared
to the normative availability. In such case a penalty at the rate
of 20% of the capacity charge shall be applicable to the extent
of the shortfall in availability.
4.6. The seller (successful bidder) shall declare availability
on a daily basis in accordance with the scheduling procedure as
stipulated in the Indian Electricity Grid Code (IEGC) from time
to time. Further the seller and procurer shall comply with all relevant
provisions of the IEGC. If the procurer does not avail generation
up to declared availability, the same can be sold in market by the
seller, and sale realization in excess of variable charges shall
be equally shared with the procurer.
4.7. Any change in tax on generation or sale of electricity as
a result of any change in Law with respect to that applicable on
the date of bid submission shall be adjusted separately.
4.8. Ratio of minimum and maximum capacity charge for any year
shall not be less than 0.7 to avoid excessive front loading or back
loading during the period of contract.
4.9. In case peakload or seasonal requirements are distinct from
baseload requirements, the bidders shall indicate distinct prices
for such peakload or seasonal supply which shall be evaluated separately.
Differential rates quoted for the same source of power for base
and peak/seasonal load shall not constitute violation of guideline
or unfair practice.
4.10. Adequate payment security shall be made available to the
bidders. The payment security may constitute:
(i) Letter of Credit (LC)
(ii) Letter of Credit (LC) backed by credible escrow mechanism.
In the case the seller does not realize full payment from the procurer
by the due date as per payment cycle, the seller may after 7 days,
take recourse to payment security mechanism by encashing the LC
to the extent of short fall or take recourse to escrow mechanism.
The procurer shall restore the payment security mechanism prior
to the next date of payment. Failure to realize payment even through
payment security mechanism shall constitute an event of payment
default. In the event of payment default the seller, after giving
7 days notice, can sell up to 25% of the contracted power to other
parties without loosing claim on the capacity charges due from the
procurer. If the payment security mechanism is not fully restored
within 30 days of the event of the payment default, the seller can
sell full contracted power to other parties without loosing claim
on the capacity charges due from the procurer. The surplus over
energy charges recovered from sale to such other parties shall be
adjusted against the capacity charge liability of the procurer.
In case the surplus over energy charges is higher than the capacity
charge liability of the procurer, such excess over the capacity
charge liability shall be retained by the seller.
Energy Charges
4.11. Where applicable, the energy charges payable during the operation
of the contract shall be related on the base energy charges specified
in the bid with suitable provision for escalation. In case the bidder
provides firm energy charge rates for each of the years of the contract
term, the same shall be permitted in the tariffs. In other cases,
the energy charges shall be payable in accordance with fuel escalation
index used for evaluation of the bid. In case of bids based on net
heat rate, the price of fuel shall be taken as stipulated under
para 4.2. However, the fuel escalation will be subject to any administered
price mechanism of Government or independent regulatory price fixation
in case of fuel produced within the country. The applicable indices
for various fuels shall be identified in the RFP documents.
4.12. No adjustment shall be provided for heat rate degradation
of the generating stations. Even in case of bids based on net heat
rate, the bidder shall factor in site conditions, loading conditions,
frequency variations etc and no adjustment shall be allowed on the
quoted net heat rate for the duration of the contract.
4.13. In case a bidder offers hydro power, under Case 1 or the
procurer invites bids of hydro power under Case 2, the hydrological
risk shall be borne by the Procurer, provided the hydrological data
of such a project is based on authentic sources and is known to
the parties in advance. Any hydrological advantages resulting in
energy availability beyond the design energy shall be passed on
to the Procurer without any charge. The geological risk for the
hydro project shall be borne by the developer.
4.14. Energy charges shall be payable by the procurer to the seller
for the scheduled energy. Deviations beyond agreed energy schedules
shall be settled under the ABT/UI mechanism.
Combined capacity and energy charges
4.15. In cases where the procurement process permits bidders to
submit combined capacity and energy charges, the charges proposed
shall be firm for each of the years of the term of the Power Purchase
Agreement (PPA), and no escalation of tariffs shall be permitted
over and above the rates proposed by the seller in the price bid.
4.16. The bidder shall specify the normative availability from
the project on an annual basis. The model PPA made available to
the bidders at the RFQ/RFP stage shall feature appropriate provisions
for penalties in event of the normative availability not being met
by the seller. The RFQ/RFP shall also specify minimum offtake conditions
for procurement from such stations.
4.17. The per kwh rates payable to the seller for offtake by the
procurer over and above the normative levels shall be the same as
the rates applicable till normative availability. In case the procurer
does not schedule the energy made available by the seller as per
the contract, the seller shall be free to sell to other parties.
The seller shall not be required to make any payments to the procurer
for such sales to third parties.
5. Bidding Process
Two-stage process
5.1. For long-term procurement under these guidelines, a two-stage
process featuring separate Request for Qualification (RFQ) and Request
for Proposal (RFP) stages shall be adopted for the bid process under
these guidelines. The procurer may, at his option, adopt a single
stage tender process for medium term procurement, combining the
RFP and RFQ processes. Procurer or authorized representative shall
prepare bid documents including the RFQ and RFP in line with these
guidelines and standard bid documents.
5.2. The procurer shall publish a RFQ notice in at least two national
newspapers, company website and preferably in trade magazines also
to accord it wide publicity. The bidding shall necessarily be by
way of International Competitive Bidding (ICB). For the purpose
of issue of RFQ minimum conditions to be met by the bidder shall
be specified by the procurer in the RFQ notice.
5.3. Procurer shall provide only written interpretation of the
tender document to any bidder / participant and the same shall be
made available to all other bidders. All parties shall rely solely
on the written communication and acceptances from the bidders.
5.4. Standard documentation to be provided by the procurer in
the RFQ shall include,
(i) Definition of Procurer’s requirements, including:
- Quantum of electricity proposed to be bought in MW. To provide
flexibility to the bidders, this may be specified as a range,
within which bids would be accepted. Further, the procurer may
also provide the bidders the flexibility to bid for a part of
the tendered quantity, subject to a given minimum quantity.
- The procurer may separately specify distinct baseload requirements
and peakload requirements through the same bid process. Seasonal
power requirements, if any, shall also be specified;
- Term of contract proposed; (as far as possible, it is advisable
to go for contract coinciding with life of the project in case
of long term procurement). The bidder shall be required to quote
tariff structure for expected life of the project depending upon
fuel proposed by him. The expected life project is estimated to
be 15 years for gas/liquid fuel based projects, 25 years for coal
based projects and 35 years for hydro projects.
- Normative availability requirement to be met by seller (separately
for peak and off-peak hours, if necessary);
- Definition of peak and off-peak hours;
- Expected date of commencement of supply;
- Point(s) where electricity is to be delivered;
- Wherever applicable, the procurer may require construction
milestones to be specified by the bidders;
- Financial requirements to be met by bidders including, minimum
net-worth, revenues, etc with necessary proof of the same, as
outlined in the bid documents;
(ii) Model PPA proposed to be entered into with the seller of electricity.
The PPA shall include necessary details on:
- Risk allocation between parties;
- Technical requirements on minimum load conditions;
- Assured offtake levels;
- Force majeure clauses as per industry standards;
- Lead times for scheduling of power;
- Default conditions and cure thereof, and penalties;
- Payment security proposed to be offered by the procurer.
(iii) Period of validity of offer of bidder;
(iv) Requirement of transfer of assets by the selected bidder
(if any) to the procurer at the end of the term of the PPA.
(v) Other technical, operational and safety criteria to be met
by bidder, including the provisions of the IEGC/State Grid Code,
relevant orders of the Appropriate Commission (e.g – the ABT
Order of the CERC), emission norms, etc., as applicable.
(vi) The procurer may, at his option, require demonstration of
financial commitments from lenders at the time of submission of
the bids. This would accelerate the process of financial closure
and delivery of electricity;
(vii) The procurer and the supplier may exercise exit option subject
to the condition that the new player satisfies all RFP conditions.
5.5. RFP shall be issued to all bidders who have qualified at the
RFQ stage. In case the bidders seek any deviations and procurer
finds that deviations are reasonable, the procurer shall obtain
approval of the Appropriate Commission before agreeing to deviation.
The clarification/revised-bidding document shall be distributed
to all who had sought the RFQ document informing about the deviations
and clarifications. Wherever revised bidding documents are issued,
the procurer shall provide bidders at least two months after issue
of such documents for submission of bids.
5.6. Standard documentation to be provided by the procurer in
the RFP shall include,
(i) Structure of tariff to be detailed by bidders;
(ii) PPA proposed to be entered with the selected bidder.
The model PPA proposed in the RFQ stage may be amended based on
the inputs received from the interested parties, and shall be provided
to all parties responding to the RFP. No further amendments shall
be carried out beyond the RFP stage;
(iii) Payment security to be made available by the procurer.
The payment security indicated in the RFQ stage could be modified
based on feedback received in the RFQ stage. However no further
amendment to payment security would be permissible beyond the RFP
stage.
(iv) Bid evaluation methodology to be adopted by the procurer
including the discount rates for evaluating the bids.
The bids shall be evaluated for the composite levellised tariffs
combining the capacity and energy components of the tariff quoted
by the bidder. In case of assorted enquiry for procurement of base
load, peak load and seasonal power, the bid evaluation for each
type of requirement shall be carried out separately. The capacity
component of tariffs may feature separate non-escalable (fixed)
and escalable (indexed) components. The index to be adopted for
escalation of the escalable component shall be specified in the
RFP. For the purpose of bid evaluation, median escalation rate of
the relevant fuel index in the international market for the last
30 years for coal and 15 years for gas / LNG (as per CERC’s
notification in (vi) below) shall be used for escalating the energy
charge quoted by the bidder. However this shall not apply for cases
where the bidder quotes firm energy charges for each of the years
of proposed supply, and in such case the energy charges proposed
by the bidder shall be adopted for bid evaluation. The rate for
discounting the combination of fixed and variable charges for computing
the levellised tariff shall be the prevailing rate for 10 year GoI
securities;
(v) The RFP shall provide the maximum period within which the
selected bidder must commence supplies after the PPA is entered
into by the procurer with the selected bidder, subject to the obligations
of the procurer being met. This shall ordinarily not be less than
four years from the date of signing of the PPA with the selected
bidder in case supply is called for long term procurement. The RFP
shall also specify the liquidated damages that would apply in event
of delay in supplies.
(vi) Following shall be notified and updated by the CERC every
six months for the purpose of bid evaluation:
1. Applicable discount rate
2. Escalation rate for coal
3. Escalation rate for gas /LNG
4. Inflation rate to be applied to indexed capacity charge component.
Bid submission and evaluation
5.7. To ensure competitiveness, the minimum number of qualified
bidders should be at least two other than any affiliate company
or companies of the procurer. If the number of qualified bidders
responding to the RFQ/RFP is less than two, and procurer still wants
to continue with the bidding process, the same may be done with
the consent of the Appropriate Commission.
5.8. Formation of consortium by bidders shall be permitted. In
such cases the consortium shall identify a lead member and all correspondence
for the bid process shall be done through the lead member. The procurer
may specify technical and financial criteria, and lock in requirements
for the lead member of the consortium, if required.
5.9. The procurer shall constitute a committee for evaluation
of the bids with at least one member external to the procurer’s
organisation and affiliates. The external member shall have expertise
in financial matters / bid evaluation. The procurer shall reveal
past associations with the external member - directly or through
its affiliates - that could create potential conflict of interest.
5.10. Eligible bidders shall be required to submit separate technical
and price bids. Bidders shall also be required to furnish necessary
bid-guarantee along with the bids. Adequate and reasonable bid-guarantee
shall be called for to eliminate non-serious bids. The bids shall
be opened in public and representatives of bidders desiring to participate
shall be allowed to remain present.
5.11. The technical bids shall be scored to ensure that the bids
submitted meet minimum eligibility criteria set out in the RFP documents
on all technical evaluation parameters. Only the bids that meet
all elements of the minimum technical criteria set out in the RFP
shall be considered for further evaluation on the price bids.
5.12. The price bid shall be rejected if it contains any deviation
from the tender conditions for submission of price bids.
5.13. Wherever applicable, the price bid shall also specify the
terminal value payable by the Procurer for the transfer of assets
by the selected bidder in accordance with the terms of the RFP.
5.14. The bidder may quote the price of electricity at the generating
station bus-bar (net of auxiliaries), or at the interface point
with the State transmission network. For purposes of standardization
in bid evaluation, the tariffs shall be compared at the interface
point of the generator/supplier with the State transmission network.
In case the bidder quotes his rate at the generating station bus-bar,
normative transmission charges for the regional/inter-regional network,
if applicable, based on the prevailing CERC orders shall be added
to the price bid submitted. The charges for the State transmission
network shall be payable by the procurer, and shall not be a part
of the evaluation criteria.
5.15. The bidder who has quoted lowest levellised tariff as per
evaluation procedure, shall be considered for the award. The evaluation
committee shall have the right to reject all price bids if the rates
quoted are not aligned to the prevailing market prices.
Deviation from process defined in the guidelines
5.16. In case there is any deviation from these guidelines, the
same shall be subject to approval by the Appropriate Commission.
The Appropriate Commission shall approve or require modification
to the bid documents within a reasonable time not exceeding 90 days.
Arbitration
5.17. The procurer will establish an Amicable Dispute Resolution
(ADR) mechanism in accordance with the provisions of the Indian
Arbitration and Conciliation Act, 1996. The ADR shall be mandatory
and time-bound to minimize disputes regarding the bid process and
the documentation thereof.
If the ADR fails to resolve the dispute, the same will be subject
to jurisdiction of the appropriate Regulatory Commission under the
provisions of the Electricity Act 2003.
Time Table for Bid Process
5.18. A suggested time-table for the bid process is indicated below.
The procurer may give extended time-frame indicated herein based
on the prevailing circumstances and such alterations shall not be
construed to be deviation from these guidelines.
| Event |
Elapsed Time from Zero date |
| Publication of RFQ |
Zero date |
| Submission of Responses of RFQ |
60 days |
| Shortlisting based on responses and issuance of RFP |
90 days |
| Bid clarification, conferences etc |
150 days |
| Final clarification and revision of RFP |
180 days |
| Technical and price bid submission |
360 days |
| Shortlisting of bidder and issue of LOI |
390 days |
| Signing of Agreements |
425 days |
5.19 A suggested time-table for the Single stage bid process is
indicated below. The procurer may give extended time-frame indicated
herein based on the prevailing circumstances and such alterations
shall not be construed to be deviation from these guidelines.
| Event |
Elapsed Time from Zero date |
| Publication of RFP |
Zero date |
| Bid clarification, conferences etc. & revision of RFP |
90 days |
| Technical and price bid submission |
180 days |
| Short-listing of bidder and issue of LOI |
210 days |
| Signing of Agreements |
240 days |
6. Contract award and conclusion
6.11. The PPA shall be signed with the selected bidder consequent
to the selection process in accordance with the terms and conditions
as finalized in the bid document before the RFP stage.
6.12. Consequent to the signing of the PPA between the parties,
the evaluation committee shall provide appropriate certification
on adherence to these guidelines and to the bid process established
by the procurer.
6.13. The procurer shall make evaluation of bid public by indicating
terms of winning bid and anonymous comparison of all other bids.
The procurer shall also make public all contracts signed with the
successful bidders.
6.14. The final PPA along with the certification by the evaluation
committee shall be forwarded to the Appropriate Commission for adoption
of tariffs in terms of Section 63 of the Act.
Sd/-
(Ajay Shankar)
Additional Secretary to the Government of India
|